Planned Work - Cable Move - Denmark, Tåstrup - CHG0026788

Scheduled Maintenance Report for Nordisk Film Cinemas

Completed

The scheduled maintenance has been completed.
Posted Sep 03, 2020 - 06:05 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 03, 2020 - 00:05 CEST

Scheduled

Reason for this change activity:

We need to move our fibre cable due to construction work

During the planned work, the existing cable will be cut, moved and re-spliced onto the new path.

Location:

Estimated downtime is up to 6 hours for services not protected.
Posted Aug 20, 2020 - 15:25 CEST
This scheduled maintenance affected: Nordisk Film Biografer (nfbio.dk, connectapi.nfbio.dk) and Nordisk Film Kino (nfkino.no, wwwapi.nfkino.no).